This is a port expansion project (Phase II) in Da Nang, Vietnam, carried out in December 2022 together with a local contractor, THIEN AN. The scope was pile foundation work: 1200 mm casings driven to 25.4 m into hard rock under the seabed, on a working quay where space and access were both tight.
Conventional rotary drilling proved too slow in that ground, so we introduced a technique new to the site: a large-diameter DTH hammer driving a 1200 mm rotary bit, with five air compressors supplying 45 m³/min at 20 bar. The hammer breaks the rock at the bottom of the hole while the casing follows, which keeps the hole stable in loose marine layers and lets the crew keep a straight line through the rock socket.
The result was a steady production rate of about two piles per day instead of the slow progress the contractor had been getting, and the method was kept for the rest of the phase. Equipment, air package and bits were supplied and supported by our team for the duration of the works.